athermalwill t1_jdta7yr wrote

The best way to do it is to screw strapping perpendicular to the joists and shim all the strapping to the lowest joist. You then screw the drywall (plasterboard) to the strapping.

1

Scoobymenace OP t1_jdtcs9l wrote

Ah yep makes sense. Plasterboard is already installed at a tilt however so will need to measure, shim the far side then plaster until level.

1