>"As part of a major $221 million climate resilience plan, the Battery Park City Authority will tear down Wagner Park, reconstruct it with new flood-prevention features and raise it by 10 feet."

No. You are wrong.

9

Sufficient-Aspect77 t1_jds20b0 wrote

My Haiku

No YOU are wrong, here!!

Water SHOULD destroy us all.

Oh wait, you were right.

3

MandatoryDissent55 t1_jdrh5ea wrote

>$221,000,000

Wagner park is hardly larger than a soccer field.

They won't elevate the Jewish Museum, so the north part will just be a wall. They can't elevate the boathouse, so the south part will just be a wall...

Snap out of this trance where you just repeat media. You're not making any sense.

−2

mowotlarx t1_jdsrjtp wrote

You are suggesting a park is being demolished and rebuilt with a flood wall not because climate change is real but because it's a grand conspiracy of government officials making up fake projects to give money to construction companies.

But, sure, I am in a trance.

3

MandatoryDissent55 t1_jdssgww wrote

You are suggesting that $221M is being spent legitimately to raise a 200' by 600' park...

...The entire park, you claim is being raised without leaving street level areas with walls, even though that park contains two very large landmarks which border the waterfront and cannot be raised.

0

mowotlarx t1_jdsvx3z wrote

So how much do you think it costs to demolish and rebuild a coastal park in Manhattan? I'd love to hear how you've scoped this out.

3

MandatoryDissent55 t1_jdt12qg wrote

They're demolishing a sunbathing platform and a few hundred feet of footpaths, then packing down landfill and walling off sections while laying new footpaths and some sod and saplings.

$20,000,000 would be overly expensive. Anything above that is going to corruption.